STRUCTURAL RETROFITTING of SKYWAY COLUMN CANTILIVER BEAM ( PASAY 3 – DON BOSCO EXIT )

Client: Skyway O & M Corp. Operator: Philippine Coastal Stroage and Pipeline Corporation Services: Material Supply Sikament R4P1 Sikagrout 212 Sikadur 31 Sikadur 752 Sikadur 732 Sikagrout 42 Sikafloor Epocem 81 Location: Pasay Off Ramp, Makati Maintenance works was immediately scheduled due to cracks manifestation on cantiliver beam of Pier Column along Pasay on 3…

STRUCTURAL RETROFITTING of SKYWAY COLUMN COPING BEAM ( Dona Soledad – Bicutan Exit )

Client: Skyway O&M Corp. Operator: Skyway O&M Corp. Services: Supply & application os structural strengthening Sikagrout 212 Sikadur 31 Sikadur 752 Sikadur 732 Sikagrout 42 Sikawrap 230C Sikadur 330 Location: SBMA Subic, Zambales Maintenance works was immediately scheduled due to cracks manifestation on Column Coping beam of Pier along Dona Soledad Ramp on Bicutan Exit…

Philippine Coastal Storage and Pipeline Corporation Fuel Storage Expansion

Client: Seaborne  Water & Construction Operator: Philippine Coastal Stroage and Pipeline Corporation Services: Material Supply Sikament R4P1 Sikagrout 212 Sikadur 31 Sikadur 752 Sikadur 732 Sikagrout 42 Sikafloor Epocem 81 Location: SBMA Subic, Zambales Philippine Coastal Storage and Pipeline Corporation (PCPSC) has successfully completed the construction of additional storage capacity and loading facilities at its…

Santa Rita Power Plant Project

Client: Siemens Power Operation Inc. Operator: Siemens Power Operation Inc. Services: Supply and application of Grouting system Sikagrout 212 / 215 Sikadur 32 Location: Sta. Rita Batangas Owned and operated by First Gas Power Corporation (FGPC), the Santa Rita plant is a 1,000-MW combined-cycle natural gas-fired power plant. Operations and Maintenance (O&M) of the plant…

AES First Battery-based Energy Storage Facility in the Philippines

Client: Sta. Clara International Corporation Operator: AES Philippines Services: Supply and application of concrete repair system Sikadur 752 Sikadur 31 Location: Masinloc, Zambales AES recently finished the constrution its First Battery-based Energy Storage array at Masinloc in Zambales, which will provide 10 MW of interconnected capacity and enhance the reliability of the Luzon grid. The…

LA MESA DAM BUFFER WALL/SPILLWAY REHABILITATION PROJECT

Client: Sta. Clara Intl. Corp. Operator: Maynilad Phils. Services: Supply and application of concrete repair system Sikadur 752 Sikadur 31 Sikatop 122 Location: Fairview, Quezon City The La Mesa Dam and Reservoir is an earth  dam whose reservoir can hold up to 50.5 million cubic meters and occupying an area of 27 square kilometers in Quezon City, Philippines. It was built in 1929…

International Container Terminal Services Inc. Project

Client: Seaborne Construction Corporation Operator: International Container Terminal Services Inc. Services: Supply and application of Chemical Anchor Sikadur 42 Sikagrout 215 Location: Port Area, Manila International Container Terminal Services, Inc.’s (ICTSI) flagship Manila International Container Terminal (MICT), the Philippines’ leading international trading gateway, is now capable of handling the world’s largest container ships after taking delivery…