Client:

First Balfour Phils. Inc.

Operator:

FPIC
Shell Phils. Inc.

Services:

Supply and application of Epoxy crack injection system

  • Sikadur 752
  • Sikadur 31
Location:

San Lorenzo, Guimaras

The San Lorenzo wind farm formally began operations with its 27 wind turbines each generating 2 MW last year. The wind farm spans 14 kilometers across four barangays in the municipality of San Lorenzo province of Guimaras.

Technocrete was contracted to undertake critical crack repair works on each foundation before erection of 75m high tubular steel tower hub turbines. Epoxy crack injection and crack repair was done to all foundations  to improved structural stability of the structures.

Technocrete was chosen because of its outstanding safety record, the ability to mobilize a highly skilled workforce to the project site and its commitment to the highest quality standards.