La Mesa Dam Water Treatment Plant (WTP) Rehabilitation Project

Client: Sta. Clara Intl. Corp. Operator: Maynilad Corp. Services: Supply and Application; Tank Lining & auxillary) (Sikagard Epocem 720) (Sikagard Epocem 62) (Sika Armatec 110) (Sikarepair 224) (Sika Injection 201) (Sikawater plug) (Sikaflex Pro 3W) ( Sikagrout 212) Location: Fairview, quezon City La Mesa Treatment Plant 1 is a conventional-type plant with a maximum design…

JTI (Japan Tobacco Inc.) Flex Project

Client: Sta Clara Intl. Corp. Operator: JTI Phils. Inc. Services: Supply and Application: Concrete Floor Hardener (Sikafloor Curehard 24) Concrete Epoxy Flooring (Sikafloor 261 SL) Tank waterproofing (BrushBond TGP) Tank Epoxy coating (Nitocoat EP405) Epoxy crack injection (Sikadur 752/ Sikadur 31) Location: Malvar, Batangas 3 Billion Project Tobacco Product Manufacturing Company. This industry stem and…

150 MW BURGOS WIND FARM PROJECT 4

Client: First Balfour Corp. Vestas Corp. Operator: EDC Burgos Wind Power Corp. Services: Structural strengthening Control Room basement Epoxy crack injection (Sikadur 752) Crack sealing: (Sikadur 31) Grouting (Sikagrout 212) Location: Burgos, Ilocos Norte The 150 MW Burgos Wind Farm is the largest wind power project in Southeast Asia. First Balfour was sub-contracted by Vestas for the…

Unilever Mega Distribution Center Warehouse

Client: Fast Services Corppration Operator: Unilever Philippines Services: Installation of Floor Hardener Area: 70,000 sq.m (Sikafloor Curehard) Epoxy Floor Area: 1,500 sq.m (Sikafloor 261) Location: Cabuyao, Laguna Unilever had completed its construction of the Largest Distribution Center in the Philippines. Spanning 13.7 hectares, the distribution center is located at the heart of Luzon’s manufacturing and…

150 MW BURGOS WIND FARM PROJECT 3

Client: First Balfour Corp. Vestas Corp. Operator: EDC Burgos Wind Power Corp. Services: Supply and application of waterproofing works Sikatop Seal 107 Location: Burgos, Ilocos Norte The 150 MW Burgos Wind Farm is the largest wind power project in Southeast Asia. First Balfour was sub-contracted by Vestas for the civil works of the 150MW wind farm. Technocrete…

150 MW BURGOS WIND FARM PROJECT 2

Client: First Balfour Corp. Vestas Corp. Operator: EDC Burgos Wind Power Corp. Services: Structural strengthening  RCBC By-Pass Bridge Sikawrap 230C Sikadur 330 Sikadur 752 Sikadur 31 Location: Burgos, Ilocos Norte The 150 MW Burgos Wind Farm is the largest wind power project in Southeast Asia. First Balfour was sub-contracted by Vestas for the civil works of the…

150 MW BURGOS WIND FARM PROJECT

Client: First Balfour Corp. Vestas Corp.   Operator: EDC Burgos Wind Power Corp.   Services: Concrete foundation repair system Epoxy crack injection (Sikadur 752) Crack sealing: (Sikadur 31)   Location: Burgos, Ilocos Norte The 150 MW Burgos Wind Farm is the largest wind power project in Southeast Asia. First Balfour was sub-contracted by Vestas for the civil…